Water Main Replacement – July to October
Please be advised that water main construction will begin on Thursday, July 8, 2021. There may be limited access to your driveway during construction hours. Additional notices will be sent out in the event of any water service interruptions.
If you have any questions, please contact someone from the construction team listed below. Any other questions after 5:00 p.m., please contact the Montclair Water Bureau at 973-744-4600.
John Garcia Construction Co. – John Garcia, 973-390-3728
H2M Architects & Engineers – Abbas Turab, 201-983-2086
Water Main Replacement Project
Construction Schedule for Oakcroft Avenue Area
- Water Main on Godfrey Road & side streets: 8/30/21 – 9/16/21
- Water Services: 9/17/21 – 10/1/21
- Tie in on Princeton Place, Edgemont Road and Carteret Street: 10/4/21 – 10/6/21
- Tie in on North Mountain Ave 10/7/21-10/12/21
- Site Restoration 10/13/21
Note: Dates may vary due to unforeseen utility conflicts and weather-related issues.